August 30: Seidel Concrete contractor, Randy Seidel, (605) 431-5388 arrives for footing preparation and squaring the building footprint. |
|||||||||||||||||||||||||||||||||||||
September 14: Forms for the footings are created |
|||||||||||||||||||||||||||||||||||||
September 17th: Concrete trucks arrive to pour the footings |
|||||||||||||||||||||||||||||||||||||
September 21st: Forms are created for the basement walls |
|||||||||||||||||||||||||||||||||||||
September 25: Rebar almost completed |
|||||||||||||||||||||||||||||||||||||
September 29th: Concrete poured for basement walls |
|||||||||||||||||||||||||||||||||||||
September 30th: Hauled in 150 tons of dirt for backfill of foundation walls |
Forms are removed from the walls |
|||||||
October 4th: Waterproof the concrete walls |
|||||||
October 6th: For the past week I’ve hauled in 250 tons of fill dirt to level off the garage floor and backfill the exterior walls |
|||||||
October 7th: Used a large portion of the fill dirt to fill in the garage floor, tamped it down and added 3 inches of gravel to level it for floor drains |
Began backfill of east wall |
Drain pipe for foundation will be covered with 5” of 1-2” gravel then back filled with fill dirt and tamped. 24, 2” foam boards to insulate the concrete walls are rsting on the trailer |
|
||
30 tons of gravel for the foundation drain pipe |
||||||||||||||||||||||||||||
October 8th: Ran out of fill dirt for backfilling the foundation |
||||||||||||||||||||||||||||
Ran a foundation drain around the perimeter (black hose) |
||||||||||||||||||||||||||||
Finish adding gravel to the basement floor, tamp and level it out |
||||||||||||||||||||||||||||
October 12th: Hauled in more dirt, brought front of house to grade |
||||||||||||||||||||||||||||
More fill needed along the south side |
||||||||||||||||||||||||||||
October 15th: Looking good across the garage door bays, floors set to grade for concrete |
||||||||||||||||||||||||||||
Two floor drains are set in the garage floor |
||||||||||||||||||||||||||||
Expansion joints are place around the perimeter - this will be the utility room for electric, well and hot water heater |
||||||||||||||||||||||||||||
October 18th: First concrete pour for the garage floor |
||||||||||||||||||||||||||||
October 19th: Second pour |
||||||||||||||||||||||||||||
October 20th: Third pour, slab completed |
||||||||||||||||||||||||||||
October 21st: Apron set up |
||||||||||||||||||||||||||||
October 22nd: Last pour |
||||||||||||||||||||||||||||
Randy, Seidel Concrete and Fawn, Croell Redi-Mix, our favorite driver - bid goodbye to another job well done! |
||||||||||||||||||||||||||||